Vidyalelo
Mechanical Engineering · all questions

Industrial Engineering And Production Management
practice.

Practice every MCQ with options. Use Show answers when you want the correct option and solution.

314

Questions

15/16

Page

Pick an option on a question to see the right answer and solution.

Break-even analysis shows profit when

Select an option to see the answer and solution.

PERT analysis is based upon

Select an option to see the answer and solution.

Pessimistic time is

Select an option to see the answer and solution.

The appellate authority for an industrial dispute is

Select an option to see the answer and solution.

Choose the wrong statement. Motion study is used for

Select an option to see the answer and solution.

The basic difference between PERT and CPM is that

Select an option to see the answer and solution.

Value engineering aims at finding out the

Select an option to see the answer and solution.

Process layout is employed for

Select an option to see the answer and solution.

Product layout is employed for

Select an option to see the answer and solution.

Bar chart is suitable for

Select an option to see the answer and solution.

Abbreviated work factor data is applied for

Select an option to see the answer and solution.

The allowed time for a job equals standard time plus

Select an option to see the answer and solution.

The type of layout used for manufacturing steam turbines, is

Select an option to see the answer and solution.

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

Select an option to see the answer and solution.

The type of organisation preferred for a steel industry, is

Select an option to see the answer and solution.

The bonus increases in proportion to the increase in efficiency. This statement applies to

Select an option to see the answer and solution.

Critical path on PERT/CPM chart is obtained by joining the events having

Select an option to see the answer and solution.

Critical path method

Select an option to see the answer and solution.

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

Select an option to see the answer and solution.

The standard time for a job is

Select an option to see the answer and solution.