Vidyalelo
Civil Engineering · all questions

Construction Planning And Management
practice.

Practice every MCQ with options. Use Show answers when you want the correct option and solution.

158

Questions

6/8

Page

Pick an option on a question to see the right answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the incorrect statement from the following:

Select an option to see the answer and solution.

Pick up the incorrect statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the correct statement from the following:

Select an option to see the answer and solution.

Pick up the incorrect statement from the following:

Select an option to see the answer and solution.

Select the correct statement.

Select an option to see the answer and solution.

Select the incorrect statement.

Select an option to see the answer and solution.

Select the incorrect statement.

Select an option to see the answer and solution.

Select the incorrect statement.

Select an option to see the answer and solution.

Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control.
of following statements

Select an option to see the answer and solution.

The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

Select an option to see the answer and solution.

The basic action involved in sheep foot rolling is

Select an option to see the answer and solution.

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be

Select an option to see the answer and solution.

The constraints in case of resource smoothening operation would be

Select an option to see the answer and solution.

PERT is

Select an option to see the answer and solution.