Vidyalelo
Civil Engineering · all questions

Construction Planning And Management
practice.

Practice every MCQ with options. Use Show answers when you want the correct option and solution.

158

Questions

7/8

Page

Pick an option on a question to see the right answer and solution.

While scheduling a project by C.P.M.

Select an option to see the answer and solution.

Final technical authority of a project lies with

Select an option to see the answer and solution.

The technique for establishing and maintaining priorities among the various jobs of a project, is known

Select an option to see the answer and solution.

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Select an option to see the answer and solution.

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Construction Planning and Management mcq question image

Select an option to see the answer and solution.

The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
Construction Planning and Management mcq question image

Select an option to see the answer and solution.

Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

Select an option to see the answer and solution.

Which one of the following represents an event?

Select an option to see the answer and solution.

The reduction in project time normally results in

Select an option to see the answer and solution.

In the given figure, the network of a project represents
Construction Planning and Management mcq question image

Select an option to see the answer and solution.

Which of the following earth moving machines has the shortest cycle time?

Select an option to see the answer and solution.

A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be

Select an option to see the answer and solution.

Completion of an activity on CPM network diagram, is generally known

Select an option to see the answer and solution.

Grader is used mainly for

Select an option to see the answer and solution.

Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

Select an option to see the answer and solution.

Site order book is used for recording

Select an option to see the answer and solution.

Which of the following does not represent an activity?

Select an option to see the answer and solution.

Sinking fund is

Select an option to see the answer and solution.

Sensitivity analysis is a study of

Select an option to see the answer and solution.

In resources levelling

Select an option to see the answer and solution.